Packaging systems configured around your application Defined project scope

Share your requirements • sales@ewpackmachinery.com

Stand-Up Pouch Machine FAT Checklist: What to Test Before Shipment

Updated: August 17, 2026
About INMAYPACK Engineering Team
With 15+ years in flexible packaging machinery, the INMAYPACK team in Shanghai has delivered doypack, sachet, premade pouch and coffee capsule filling lines to customers in international markets. We don't just sell machines — we study your product, material and target speed, then configure a complete, application-matched packing solution that runs reliably for years. Every article here comes from real factory floors and real customer projects.
Capital equipment acceptance · Published July 27, 2026

A running machine is not yet an accepted machine. A factory acceptance test should prove that the agreed machine, pouch, product and operating conditions work together—and leave an auditable record of what passed, what failed and what remains open before shipment.

Quick answer: freeze the FAT protocol before the test; bring production-representative film, product and coding materials; verify scope, safety functions, recipes, alarms and manual modes; run approved pouch formats under defined conditions; measure package quality and performance against contract values; test the agreed changeover; then close or formally assign every deviation. Do not invent pass limits on the test day.

HMK2000 stand-up pouch packing machine prepared for factory acceptance testing
A FAT must cover the complete contracted machine scope, including the pouch-forming section, filler interfaces, controls, guards and agreed downstream equipment—not only a short no-load demonstration.

The checklist below is written for a roll-stock stand-up pouch machine. It does not replace the signed user requirement specification, purchase contract, approved drawings or project-specific FAT protocol. Those documents control the acceptance values.

Before the test

Freeze the acceptance basis before anyone travels

A FAT cannot resolve an undefined purchase scope. The buyer and machine builder should agree the protocol, test materials, responsibilities and evidence format while there is still time to prepare the machine and samples.

1. Contract baseline

List the machine model, filler, conveyors, coder, inspection devices, guarding, utilities, software options, spare parts and documentation included in the order.

2. Approved formats

Identify every pouch size and construction to be witnessed. Attach the approved pouch drawing, film specification, print repeat and registration-mark information.

3. Real test materials

Define who supplies film, zipper, product, coding consumables and packaging for samples. Record batch or roll identification so results remain traceable.

4. Acceptance values

State target speed, run duration, sample frequency, fill tolerance, allowable rejects, seal tests and changeover expectations exactly as agreed for the project.

5. Witness team

Name the people authorized to observe, measure, accept deviations and sign the report. Include production, engineering, quality and safety roles where applicable.

6. Evidence package

Agree which data, photographs, videos, sample pouches, alarm records, drawings and signed forms will be delivered after the test.

Critical rule: “maximum machine speed” is not automatically the FAT acceptance speed. The pass value must correspond to the contracted pouch, product, filler and quality conditions. Likewise, a generic run duration or reject percentage should never be added after the purchase order unless both parties approve the change.

The OpX One Voice acceptance-test work product exists to reduce unclear FAT, vFAT and SAT expectations between equipment users and OEMs. For the pouch machine itself, also lock the incoming roll data using the doypack film specification checklist.

Functional and safety checks

Prove the controls before measuring output

Start with identification and dry-cycle checks. Confirm the equipment supplied matches the approved scope, utilities are within the declared range and the machine can be operated, stopped and recovered as intended.

  1. Identification and construction. Confirm model and serial identification, machine direction, materials of construction, access, supplied assemblies and the latest approved layout.
  2. Utilities and interfaces. Record electrical supply, compressed air, vacuum, extraction and any product-feed or downstream connections used during the test.
  3. Manual and setup modes. Jog each relevant actuator under controlled conditions and confirm access, direction, labels and setup permissions.
  4. Guards and protective functions. Test the agreed emergency stops, guard-door interlocks, restart behavior and fault reset sequence. Record each device, result and unresolved exception.
  5. Alarms and fault recovery. Challenge agreed conditions such as missing film, registration loss, low air, temperature deviation or filler-not-ready signals where the machine design supports them.
  6. Recipes and access levels. Verify approved pouch recipes, editable fields, units, user permissions, data retention and backup or restore method included in the project.
Guarded pouch-forming station for machine safety function checks
Guard doors and access points are test items, not decoration. The FAT record should identify the protective function tested and the observed machine response.
Packaging machine HMI and emergency stop controls checked during FAT
The HMI review should use the approved project functions and recipes. A screenshot alone does not prove alarm logic, permissions or recovery behavior.

Machinery risk assessment and risk reduction are addressed by ISO 12100. Electrical equipment of machinery, including topics such as protective bonding, emergency-stop control functions and technical documentation, is addressed by IEC 60204-1. The applicable standards and conformity scope must be defined for the destination and project; this article is not a compliance certificate.

Production-representative run

Measure the package, not only the cycle counter

Run the agreed film and product through the complete process path. Start-up scrap, steady-state output, planned stops and fault stops should remain distinguishable in the record so that a good average cannot hide an unstable period.

Test familyWhat to define before FATEvidence to retain
Pouch geometryApproved width, height, gusset, cut position, notch, zipper or hole location and permitted variationTime-stamped samples and measurements against the approved drawing
Seal and appearanceRequired seal locations, visual defects, wrinkles, channels, contamination controls and project-specific package testsSample plan, test method, results and retained good/bad reference samples
FillingProduct condition, target fill, allowable tolerance, sampling method and filler interface behaviorIndividual sample results, scale identification and exception record
Registration and codingPrint-to-cut requirement, code content, legibility, position and reject response where suppliedMarked samples, code verification and fault challenge result
Performance runContracted speed, duration, planned stops, permissible rejects and calculation methodStart/end times, counter readings, stop log, good packs and reject classification
Format changeFrom/to formats, starting condition, trained operator, included tools and end conditionElapsed time, adjustments, parts used and first acceptable package

Keep numerator and denominator visible

If the protocol uses a quality or performance percentage, the report should show the underlying counts and agreed formula—not only the final percentage. Classify losses by cause: film handling, forming, filling, sealing, coding, machine stop, planned adjustment or material defect. This makes the punch list actionable and prevents unrelated causes from being combined.

Do not substitute empty-bag success for a product run. Product dust, granules in the seal area, liquid splash, fill weight, package load and real laminate behavior can change opening, filling and sealing performance. Any approved substitute material and its limitations should be written into the protocol.

Use the stand-up pouch seal-integrity guide to define a product-and-film-specific test plan, and the HFFS troubleshooting sequence to isolate defects without changing several process families at once.

Closure and handover

A punch list needs owners, evidence and deadlines

Every deviation should be classified before the FAT meeting ends. “To be fixed” is not enough. Record the requirement, observed result, impact, agreed action, responsible party, due date and the evidence needed for closure.

Accepted: requirement met and supporting evidence attached.

Accepted with an agreed deviation: difference understood, commercially and technically approved, and incorporated into the controlled project record.

Open before shipment: corrective action and verification evidence required before release.

Deferred to SAT: test genuinely depends on site utilities, upstream/downstream integration or production conditions unavailable at the builder’s factory.

Failed: acceptance requirement not met and shipment disposition requires authorized approval.

Documents to collect before shipment release

  • Signed FAT protocol, raw results, sample identification and deviation log.
  • Approved as-built mechanical, electrical and pneumatic drawings included in the contract.
  • Operating, maintenance, lubrication, cleaning and changeover instructions included in scope; use the pouch packing machine preventive maintenance guide to check whether tasks, intervals, records and restart verification are defined.
  • PLC/HMI or recipe backups where contractually supplied, plus controlled version identification.
  • Recommended spare-parts list, supplied spare-parts inventory and applicable certificates; use the pouch packing machine spare-parts guide to verify critical, wear and commissioning classifications against the as-built machine.
  • Training attendance and open training topics for installation or SAT.

FAT is not SAT

FAT verifies the agreed equipment at the builder’s facility. SAT verifies the installed system under site conditions. Incoming power and air, floor layout, upstream product feed, downstream inspection, plant networks, operator practices and production environment can all introduce conditions that were not present during FAT.

The FAT report should therefore state what was demonstrated, what was not available and which items transfer to installation, commissioning or SAT. Passing FAT should never be written as proof of every future product, film or operating condition.

Engineering next step

Turn the purchase specification into a witnessable test

Review the HMK2000 stand-up pouch packing machine specifications, then send the agreed pouch drawings, film structure, product data, filler scope, target output and acceptance requirements. INMAYPACK can identify which materials, tooling and test conditions must be ready before the witness date.

Prepare a project-specific FAT scope

Include the machine configuration, every witnessed format, real test materials, agreed performance conditions, package-quality methods, changeover scope and documentation deliverables. Values will be reviewed against the project—not replaced with generic thresholds.

Technical references

OpX Leadership Network, One Voice for Acceptance Tests—industry guidance intended to reduce unclear FAT, vFAT and SAT criteria and responsibilities.

PMMI, OpX Leadership Network Offers Updated FAT Guidance—background on defining expectations and communication between equipment users and OEMs.

International Organization for Standardization, ISO 12100:2010—general principles for machinery risk assessment and risk reduction.

International Electrotechnical Commission, IEC 60204-1:2016—general requirements for electrical equipment of machines. Applicable editions and requirements must be confirmed for the project.

INMAYPACK Engineering Team
Shanghai · Flexible Packaging Machinery

Need a Technical Opinion?

Tell us your product, material and target speed — our engineers will recommend the exact machine configuration for your line.
✓ Reply after reviewing your requirements
✓ international markets served
✓ Configuration-specific compliance documentation
Chat on WhatsAppGet a Free Quote
☎ +86 18658799162✉ sales@ewpackmachinery.com

You Might Also Find Helpful

Tell Us Your Need

Send your requirements for a scoped technical reply.

✓ Requirements reviewed before recommendation

✓ Your info stays private

✓ Project-scoped technical review