A packaging machine site acceptance test (SAT) checks the installed system against agreed requirements at the buyer's facility. Carry the factory acceptance test (FAT) evidence forward, identify what changed during installation, and collect the site-specific results needed for an authorized handover decision.
A machine that ran at the factory still has to work with the site's utilities, product supply, operators and connected equipment. This guide helps buyers turn those differences into a test plan. For the available project support and its agreed boundaries, start with INMAYPACK service and installation support.
The matrices below are proposed purchasing and handover tools, not completed INMAYPACK SAT records or a universal acceptance standard. Test limits, responsibilities, safety procedures, service attendance and release authority must be agreed for the actual project. No fixed test duration, output or commissioning result is promised.
Start with the FAT baseline and the installation changes
FAT and SAT answer related questions at different locations. R.WEISS describes its own sequence as documented factory acceptance before shipment, followed by installation, commissioning and SAT at the customer site. The useful planning principle is to connect the two evidence sets. That supplier's service arrangements do not define the terms of an INMAYPACK project.
Collect the signed FAT report, approved specification, machine identity, software or recipe revision where applicable, drawings, sample records and open-item list. Use the stand-up pouch machine FAT checklist for the factory-stage evidence. At site, each requirement needs a clear disposition: retained evidence, an installation check, a repeat test, or a test that could not be completed at the factory.
Do not mark a requirement passed simply because it appears in the FAT report. Identify whether its conditions remain applicable. Equally, avoid repeating every factory inspection without a reason. A reviewed carryover matrix directs effort toward changed conditions and unresolved risks.
Proposed FAT-to-SAT carryover matrix. On small screens, scroll the table horizontally; keyboard users can focus it and use arrow keys.
| Requirement and factory evidence | What may change at site | Proposed site evidence |
|---|---|---|
| Approved machine, options and drawings | Shipping assembly, placement, connected devices or revised scope | Installed identity, drawing revision and recorded differences |
| Utility requirements and factory run conditions | Actual supply, distribution losses and simultaneous demand | Qualified checks and readings at the agreed connection points during operation |
| Product and package trial | Material batches, product temperature or condition, supply method | Traceable site trial using the approved product and packaging |
| Factory interface test or simulated signals | Actual upstream, inspection and downstream equipment | Observed transfers, stop states, rejects and permitted recovery |
| FAT deviations and tests deferred to site | Corrected parts, software changes or newly available equipment | Item-linked retest record and authorized disposition |
Keep commissioning adjustments separate from acceptance results. Record the final configuration before the acceptance run. If a later adjustment affects a tested function, identify which evidence it invalidates and repeat the relevant checks.
Make site readiness a documented starting condition
An acceptance visit can become an installation delay when the machine arrives before the building, materials or connected line is ready. Agree the readiness review before scheduling attendance. Name the party supplying each item and the evidence needed to call it ready; a calendar booking alone does not establish readiness.
- Placement and access
- Approved layout, installation space, transport route, service access and the relationship to adjacent equipment. Record changes from the agreed drawing.
- Utilities at the machine
- Required electrical, air, gas, water or other connections for the supplied configuration. Use qualified personnel and manufacturer-approved checks; retain conditions measured under representative demand.
- Test materials
- Approved product, pouch or film batches, labels or coding information, test instruments and enough material for the agreed sequence, including retests and rejects.
- People and authority
- Buyer and supplier contacts, connected-equipment representatives, trained operators, test witnesses and the person authorized to dispose of deviations.
Record utility conditions where the machine is connected. A central compressor nameplate is not a measurement of the air available during a production event. The packaging machine compressed-air guide explains why connection conditions and demand belong in the review. Use the approved requirements for the actual configuration rather than borrowing another model's values.
Readiness is not permission to bypass a protective function. Electrical work, installation inspections and safety-function verification must follow the approved procedures and be performed by authorized, qualified people. Record unresolved safety issues and refer them to the responsible authority before proceeding.
Check the installed handoffs before the performance run
A factory simulation can confirm intended logic without proving the final physical installation. At site, establish which machines belong inside the test boundary, where product enters, where an accepted pack leaves, and which devices were absent or simulated during FAT.
Use the packaging system integration checklist to define ownership of signals and transfers. The SAT record then identifies what was actually connected, the approved test condition, the observed response and the evidence reference. Do not treat a checked signal alone as proof of a successful product transfer.
- Normal transfer: verify orientation, spacing and product support at each physical boundary with the agreed pack.
- Starved or blocked conditions: observe the specified line response and controlled restart under an approved test method.
- Inspection and rejection: where included, trace an authorized challenge from detection through removal, confirmation and reject containment.
- Recipe and changeover: check the selected format across the devices that share it, including coding and inspection settings where supplied.
A new conveyor, relocated inspection device or software change can alter a previously tested boundary. Record the revision and assess the affected tests. Keep independent inspection-provider responsibilities visible; connection to a packaging machine does not establish a contaminant detection limit or certification.

Define accepted output under representative production conditions
Agree the product, packaging, recipe, operators, run duration and acceptance limits before the trial. Include the production events that matter to the purchase: startup, replenishment, a planned changeover or recovery may expose conditions that a short uninterrupted display does not. Select events for the real project rather than turning every possible event into a mandatory test.
Record the start and end times, raw output, accepted packs, rejects, stops and interventions on the same time basis. Define whether loading, cleaning, adjustment, changeover and restart belong within that interval. A mechanical cycle count and accepted packs over an elapsed production interval are different measures.
Keep quality observations linked to samples and events. Record the applicable fill result, seal condition, code or inspection outcome using the agreed method. Identify the instrument and its required status, material batch, recipe revision and sample disposition. A photograph of finished bags supports identification but does not replace a measurement record.
When conditions change mid-run, mark the point of change. Retain the original segment and explain any exclusion rather than deleting slow periods or pooling unlike trials. If the approved product or packaging is unavailable, document the limitation and the remaining test; a substitute trial should not silently close the original requirement.
Give every deviation a closure route and a release decision
A punch list is useful only if each item connects a requirement to an observed result and a closure owner. Keep the initial result, correction and retest together. The person performing a correction and the person authorizing acceptance may have different responsibilities; record both.
Proposed deviation and release register. These are record fields, not completed test results or universal acceptance categories.
| Record field | What to capture | Decision it supports |
|---|---|---|
| Requirement and evidence | Test ID, approved limit, actual result, sample or file reference and configuration revision | What failed, remained untested or needs clarification? |
| Impact and interim status | Affected function, product or operating condition, plus any proposed restrictions | Does the authorized reviewer permit further testing or operation? |
| Action and owner | Correction, responsible party, agreed date and dependencies | Who closes the item, with what evidence? |
| Retest and affected scope | Repeat result and any related tests affected by the change | Is the correction demonstrated without leaving affected functions unchecked? |
| Final disposition | Open, closed or otherwise explicitly authorized status, reviewer and date | What is accepted, what remains restricted and what must happen next? |
Do not convert an incomplete test into a pass because a service visit is ending. If a condition is not met, retain its status and agree the next action. Any conditional release needs the authorized decision, its scope and restrictions, not just a promise to return later.
Keep technical status and commercial authorization distinct. Delivery, payment milestones, warranty commencement and service obligations follow the applicable agreement; a generic checklist cannot define them.
Hand over the configuration people will actually operate
The final record should let another responsible person identify what was accepted without reconstructing a visit from messages. Include the installed equipment list, approved revisions, FAT carryover decisions, site readings, test results, deviation register and authorized release record.
List the applicable manuals, drawings, permitted access arrangements, recipe or software backup responsibilities, maintenance information and parts identification records. Confirm which documents are delivered and which remain outstanding. Manage credentials and backups through the agreed access procedure rather than placing sensitive access details in a general test report.
For training, record participants, language, covered tasks and the evidence of completion agreed for the project. An operator demonstration of the approved startup, stop, changeover or cleaning task is more useful than an attendance list alone when practical competence is part of the scope. Training does not authorize tasks reserved for qualified maintenance or electrical personnel.
Finish with the next contact route and the information needed for support: machine identity, revision, event time, operating condition and relevant evidence. Verify the agreed support terms rather than assuming unlimited remote assistance, included travel or a fixed response time.
Buyer questions about packaging machine SAT
Does passing FAT remove the need for SAT?
FAT provides evidence from the factory conditions and agreed scope. Review what changes during transport, installation and connection at site. The approved carryover plan determines which evidence remains applicable and which installed functions or production conditions still need testing.
How long should a site acceptance test run?
Agree the duration around the required evidence, product and pack range, production events and representative conditions. A universal number of hours cannot establish suitability for every project. Keep commissioning time, acceptance runs, stops and retests identifiable in the record.
Can a machine be handed over with open items?
Only the authorized project decision can establish an acceptable release scope. Record each unresolved item, its impact, restrictions, responsible party and closure evidence. Do not mark an untested or failed requirement passed to complete the handover paperwork.
Who supplies test materials, utilities and site engineers?
Assign these responsibilities in the quotation and acceptance plan before attendance is scheduled. Confirm product and packaging quantities, utility readiness, connected-equipment support, witnessing, travel and any additional work. Availability and charges depend on the actual agreement.
Define the site acceptance scope before scheduling attendance
Share the machine and line scope, approved product and package, available FAT evidence, site layout, utilities, connected equipment and unresolved items. INMAYPACK can review the requested support scope against the proposed configuration and project agreement.
Source and scope: R.WEISS's installation and commissioning page is linked above as a manufacturer example of the FAT-to-site sequence. The carryover matrix, readiness review and deviation register here are proposed planning tools. They do not reproduce a completed customer acceptance record or establish another manufacturer's terms as INMAYPACK policy.